Claims

Uncertain Surety: Expiration Of A Limitation Against A Principal Is Not A Defence To A Bond Claim

Sometimes failing to arbitrate a dispute with a binding arbitration provision can be fatal to a claim under a construction contract, particularly if the limitation period to commence the arbitration has expired.  But, in the case of a project with a performance bond, things can sometimes become more complex. Performance bonds are a common tool on major construction projects. They are three-party contracts: the obligee (the party to whom the obligation under the bond is owed; typically an owner, although can be a general contractor on large projects in which multiple levels of bonding are in place); the principal (the party performing the work under the bonded contract; typically a general contractor, although can be a subcontractor on large projects in which multiple levels of bonding are in place); and the surety (an insurance company). If the bonded contract proceeds without issue between the obligee and the principal, then the surety plays no role in the project. However, if issues arise between the obligee and the principal and the principal is declared to be in default of the bonded contract, then the surety is required to step in and investigate. The surety can either deny or allow the bond claim. If the claim is allowed, then the surety essentially steps into the shoes of the principal, and has the same defences available to it as against the obligee as did the principal under the bonded contract prior to its default. A Surety Cannot Rely on the Expiration of a Claim against the Principal to Deny a Bond Claim However, the Alberta Court of Appeal in HOOPP Realty Inc v Guarantee Company of North America, 2019 ABCA 443 held that the expiry of an obligee’s limitation period to sue the principal does not provide the same limitations defence to a surety in the face of a bond claim lawsuit. In that case, Clark Builders (“Clark”) was the principal/general contractor, HOOPP Realty (“HOOPP”) was the obligee/owner, and The Guarantee Company (“GCNA”) was the surety. Clark was hired to construct a warehouse. HOOPP was unhappy with the warehouse floor. Clark replaced the floor at its own cost, but argued it was not required to do so under the bonded contract. The parties agreed the performance bond would extend to the floor replacement if Clark was in default of the bonded contract. In litigation between HOOPP and Clark, the Court of Appeal held that the dispute was subject to a mandatory arbitration clause, and HOOPP could not maintain a Court action. Subsequently, the Court held that HOOPP was limitation-barred from commencing an arbitration against Clark, and as such, HOOPP could not maintain any claim, in Court or arbitration, against Clark. HOOPP had commenced a separate, parallel action against GCNA under the bond, which it continued to pursue notwithstanding the dismissal of its claim against Clark. The issue then was whether GCNA was also immune from liability to HOOPP, given that HOOPP’s claim against Clark was limitation-barred. The matter was heard via summary trial. The trial judge concluded that GCNA was not relieved of liability, as the expiry of a limitation period does not necessarily extinguish the underlying debt, but only bars the remedy against the defendant. In addition, the trial judge held that HOOPP had distinct claims against Clark and GCNA, even if those claims may overlap. The Court of appeal upheld this decision. It noted that the general statement that a surety is entitled to any defence available to the principal is accurate when related to the principal’s liability under the bonded contract. However, when the issue is whether the surety is directly liable to the obligee, that is a separate issue. The Court confirmed that the surety’s liability under the bond required that the principal had defaulted under the bonded contract. But in the facts at bar, where there was an alleged default by the principal, the obligee had a potential independent claim against both the principal and the surety. This was supported by the bond wording in this case, which provided that the surety and principal were jointly and severally liable under the bond. In addition, the Court noted that an obligee is not required to exhaust all remedies against the principal in order to advance a claim against a surety. While HOOPP in this case had made an attempt to sue Clark, the Court noted that the outcome of the appeal would have been the same even if no such attempt had been made. Finally, the Court rejected GCNA’s argument that by permitting HOOPP’s claim against GCNA to proceed, it was allowing HOOPP to indirectly pursue Clark. GCNA argued that if HOOPP made a successful claim against GCNA, GCNA would then have an indemnity claim against Clark; i.e. in the end, Clark would still be liable for HOOPP’s claim despite the expiration of HOOPP’s limitation period to sue Clark directly.   The Court held that Clark, as principal, did not have the protection of a limitations defence until the limitation had expired against both it as principal and GCNA as surety. Similarly, GCNA, as surety, did not have the protection of a limitations defence until the limitation had expired against both it as surety and Clark as principal. In other words, if GCNA was held liable to HOOPP, GCNA could then pursue an indemnity claim against Clark. While many of the Court’s comments were general principles applying to all performance bonds, in the end it was clear that the result on this appeal depended on the wording of the GCNA bond. In particular, the Court noted there was nothing in this bond requiring HOOPP to exhaust its remedies against Clark in order to maintain a bond claim against GCNA. The Supreme Court of Canada has now refused leave to appeal for this matter, so it remains the law applicable in Alberta.  The case adds another level of complexity when trying to assess limitation periods in the context of projects with mandatory arbitration provisions coupled with separate performance bonds. https://www.jdsupra.com/legalnews/uncertain-surety-expiration-of-a-74015/

Uncertain Surety: Expiration Of A Limitation Against A Principal Is Not A Defence To A Bond Claim Read More »

Surety bond at issue in Merchants Greene contractor’s bankruptcy [CNA]

The cessation of operations at Trent-Wyatt Contracting, a Jefferson City-based company that had a large erosion-control contract at the Merchants Greene development in Morristown, has created a complicated legal wrangle involving city government and Western Surety, Trent-Wyatt’s former bonding company, officials say. Trent-Wyatt obtained a bond through Western Surety that guaranteed erosion-control work, including a piping system and catch basins to convey runoff to a retention pond, would be completed. If Trent-Wyatt didn’t perform the work, Western Surety would be on the hook for construction costs. On June 5, 2019, however, Western gave a 30-day notice it was terminating its liability under the erosion-control bond, according to Morristown City Attorney Lauren Carroll. That date is important because it’s 29 days after one of Trent-Wyatt’s owners, Kevin L. Trent, filed for personal Chapter 7, or liquidation, bankruptcy. The other company owner, Gary W. Wyatt, filed for personal Chapter 7 bankruptcy on July 11. Both Trent and Wyatt estimated their liabilities range from $10 million to $50 million, according to their bankruptcy filings. Western Surety was released from the erosion-control about nine months ago. What complicates matters, Carroll says, is calculating how much work remained when Western Surety was released from the bond. Carroll and Michael Poteet, Morristown stormwater coordinator, estimate it will cost approximately $750,000, and that’s the amount Carroll is seeking to recover from Western. On Thursday, Carroll declined to identify how much Western Surety is willing to pay, but the city attorney did say it was “substantially less” than $750,000. Morristown real estate developer Shannon Greene, one of the developers of the Merchants Greene property in West Morristown, said Thursday the dispute between Morristown government and Western Surety has “nothing to do with him.” That’s partially correct, Carroll says. The city attorney says that while legal action is a possibility, she’s trying to negotiate a mutually acceptable settlement with Western to finish the erosion-control work. The Greene family owns the property, and ultimately is responsible for installing the stormwater system specified in the plans, according to the city attorney. Greene says it’s too early to install drainage pipes because the location of the stormwater system will be dictated by future tenants. It makes no sense, Greene says, to lay underground pipes that could run beneath a restaurant, hotel or other business. Similarly, spreading topsoil and seeding it with grass isn’t smart if it’s going to be removed in the foreseeable future, Greene says. However the erosion-control bond conflict is settled, Morristown city government and Greene are compelled to work together on other development-related matters in the future, Carroll says. Part of the tax-increment financing arrangement the Greene’s received when they began the development required them to put up a traffic signal at the intersection of West Andrew Johnson Highway and Howell Road. The proposed deadline is in the fall. Greene says it’s too early to install a traffic light. He says it makes more sense to spend the money when the road linking Merchants Green and Exit 4 of Interstate 81 is complete. That’s when he anticipates interest in Merchants Greene will dramatically increase. He says Merchants Greene has created approximately 800 new jobs, and he would appreciate a little flexibility from city government in trying economic times that have been disastrous for prospective buyers. “Nobody thought the economy would fall like this,” Greene said. The developer says that if he were to move immediately to order traffic signals, there’s no guarantee they would arrive by fall. He says the overwhelming majority of traffic light components are manufactured in China. https://www.citizentribune.com/news/local/surety-bond-at-issue-in-merchants-greene-contractor-s-bankruptcy/article_6984c51a-7b48-11ea-bbf0-a36e9321d2b3.html

Surety bond at issue in Merchants Greene contractor’s bankruptcy [CNA] Read More »

Douglas County warned activist group of $3 million surety bond if it filed lawsuit challenging jail expansion

Prior to local activist group Justice Matters filing a lawsuit last month against Douglas County’s plan to expand its jail, an attorney for the county warned that he would pursue a $3 million surety bond from the group if it went through with the lawsuit. In response, William Skepnek, an attorney representing Justice Matters, wrote a letter calling the county’s tactic one of “edict, threat and condescension.” If a court were to go along with the county’s request for a surety bond, it basically would mean that Justice Matters would have to purchase the equivalent of a $3 million insurance policy before the case could continue. Often, a surety bond also requires a business or organization to pledge its own assets if the bonding company must make a payment on the claim. In this case, the county would be seeking the bond to repay the county for costs associated with the lawsuit and to help cover any added construction costs for the jail that a lawsuit may cause. On Monday, John Bullock, the county’s attorney, disagreed with Skepnek’s characterization. He said in an email to the Journal-World that pursuing a surety bond was appropriate because Justice Matters was seeking an injunction on the county’s plans to expand the jail. If an injunction is granted, the project could be delayed and result in higher construction costs and higher interest rates on the bond market, among other increased expenses, he said. “When a party in litigation seeks an injunction, the court can require a security bond to protect the other party against losses caused by the suit,” Bullock said in an email to the Journal-World. “The county’s exercise of this statutory right is not a ‘threat,’ but a necessary measure to protect the taxpayers from significant losses expected to result from Justice Matters’ suit seeking injunctive relief.” The Journal-World reached out to the three Douglas County commissioners for comment on Bullock’s pursuit of a surety bond, but they did not immediately respond. Joanna Harader, a member of Justice Matters, recently provided the letters to the Journal-World at a reporter’s request. The three-letter correspondence between Skepnek and Bullock highlights their differing views on whether Douglas County has the legal authority to expand its jail without a new public vote. Before filing the lawsuit, Skepnek sent a letter to Bullock on Feb. 15 explaining that Justice Matters had retained him and James Kaup for legal representation and explained the group’s opposition to the expansion of the jail. He said the group had requested to send the letter and explain the reasons for its opposition in an effort to be transparent. “Among those reasons is that we believe the Douglas County Commission lacks the authority to issue the proposed bonds without first either submitting the matter to a vote, or alternatively publishing notice of its intent to issue, enabling voters to petition to place the issue on the ballot,” Skepnek wrote. In a response, dated March 5, Bullock noted the county’s previously stated rationale for the expansion without a new vote: a 1994 sales tax referendum, which created a 1-cent sales tax “for general government purposes, including the issuance of sales tax revenue and general obligation bonds, and also including … The Expansion and operations of the county jail.” Bullock said that gave the county the authority to issue bonds without voters signing off. However, if Justice Matters went through with the lawsuit, he said the county would seek the dismissal of the lawsuit on “various legal grounds.” He also said the county would pursue a surety bond from Justice Matters “to protect the taxpayers against the costs the county will suffer on account of your client’s lawsuit.” Bullock said the surety bond, which would need to be approved by the court, would be “not less than $3 million.” “We urge your clients to reconsider their plans to use litigation to advance their agenda,” Bullock said in the letter. In a second letter to the county, dated March 6, Skepnek said he was disappointed in the county’s response. He also said he and Justice Matters did not believe the court would approve such a surety bond in its challenge to the county’s legal authority to expand the jail. He, again, asked the county to consider a new public vote on the expansion of the jail. “If the citizenry of Douglas County want a jail expansion it will surely be authorized by the voters in a public contest,” Skepnek said. Justice Matters filed its lawsuit in Douglas County District Court on March 16, making the same argument that Douglas County commissioners are not allowing residents to vote or petition against the plan to fund an expansion of jail, despite the group’s belief that they have an obligation to do so under state law. Karrey Britt, a spokeswoman for the county, said the county planned to file a response to the lawsuit on Tuesday. The lawsuit is a culmination of a yearslong effort by the group and others to stop the county from expanding the jail to house more inmates. As the Journal-World has reported, county leaders say that the jail is overcrowded, making it unsafe for both staff and inmates; opponents argue that the county needs to try more alternatives to incarceration to lower the jail’s population. Two local nonprofit organizations, Justice Matters and the Lawrence Sunset Alliance, along with five individuals who reside within the county, are petitioning for an injunction to stop the county from issuing bonds to fund the planned expansion, estimated to cost roughly $29.6 million, plus a separate estimated $1.5 million renovation of the jail’s central heating and cooling plant. The county had approximately $9 million on hand to go toward the jail, the Journal-World has reported. County staff planned to pursue a bond issue with a 20-year debt service to finance the rest of the estimated $31.1 million total, which is about $22.1 million. https://www2.ljworld.com/news/county-government/2020/apr/06/douglas-county-warned-activist-group-of-3-million-surety-bond-if-it-filed-lawsuit-challenging-jail-expansion/

Douglas County warned activist group of $3 million surety bond if it filed lawsuit challenging jail expansion Read More »

Demotech Logo

Demotech Investigates Impact of COVID-19 on Surety Insurance

COLUMBUS, Ohio, April 2, 2020 /PRNewswire/ — The COVID-19 pandemic and the historic federal, state, and local government efforts to mitigate its spread has stopped the economy in its tracks. Social distancing and self-isolation may result in the US unemployment rate reaching record levels. The dialogue on business interruption insurance will continue, whether in the courts or to discuss a federal backstop. At the forefront of the issue of the ability of businesses to perform under stress is surety insurance. The insurer, as surety, is the party that guarantees the performance of another party, often a contractor or a construction project. The contract through which the guarantee is executed is a surety bond. As of December 31, 2019, there were 323 insurers that reported direct premium written for the surety insurance line of business. There are various types of surety insurance; however, the insurers that wrote performance bonds may see a rise in claim frequency and severity as a result of unemployment, constrained cash flows, and other phenomena impacting businesses. Direct premium written (DPW) for surety insurance for the 323 insurers was nearly $6.8 billion at year-end 2019. The top 20 writers, based on all types of surety insurance written, accounted for over $4.4 billion, 65 percent of the industry dollar volume. Surety insurance comprised approximately 17 percent of these top 20 insurers’ books of business and was but 3 percent of the books of business of all carriers writing some surety. Despite the diversification within many of the top 20, surety insurance constituted more than 90 percent of seven insurers’ total 2019 DPW. According to Joseph L. Petrelli, President and co-founder, Demotech, the first company to review and rate independent regional and specialty insurers, “By count, the 323 carriers writing surety insurance are nearly 13% of the Property and Casualty insurers reporting to the National Association of Insurance Commissioners. With respect to the impact of COVID-19 on surety insurers writing performance bonds, keep in mind that at the time the performance bonds were written, the economy was humming, competent contractors were likely to be at full capacity, with projects in their pipeline. COVID-19 and the response to mitigate the contagion changed everyone’s world. It is unlikely that insurers writing surety insurance will be spared from future discomfort.” A full article along with a chart of the top 20 writers of Surety Insurance by 2019 DPW can be found here. https://www.prnewswire.com/news-releases/demotech-investigates-impact-of-covid-19-on-surety-insurance-301034239.html

Demotech Investigates Impact of COVID-19 on Surety Insurance Read More »

13-lisbon-valley

Mine ordered to mitigate environmental harm; reclamation contractor is working without pay

In response to the abrupt closing of the Lisbon Valley Copper Mine, Director John Baza of the Utah Division of Oil, Gas and Mining has signed an emergency order, according to a statement from the division. The order requires that the operator contains and/or reclaims any and all facilities at the mine to the extent necessary to immediately prevent any imminent threat of environmental harm. If the operator fails to take immediate action to ensure the environmental harms are mitigated, the division will undertake emergency actions to forfeit the full amount of the surety bond. A surety bond ensures monies are available to the division for reclamation in the event the company defaults on its permit. The emergency order will apply until the next Board of Oil, Gas and Mining Board Hearing scheduled for April 22. An inspector from the Bureau of Land Management inspected the site early Friday. A division inspector is now onsite. “Our main objective is to ensure the facility poses no threat to the surrounding environment and that there are no risks to public safety,” said a statement from the division. According to the operator’s annual report, the mine is 984 acres in size and includes four pits, one leach pad, approximately four water process ponds, and several buildings. On Monday, March 23, inspectors from the Division of Oil, Gas and Mining confirmed for the operator steps that will need to be taken to avoid potential off-site impacts. Any work that’s done can only be shutdown or reclamation related; no production work can occur. The surety that holds the bond for Lisbon Valley Mining Company has been contacted while a contractor develops a shutdown plan for the mine. The surety bond ensures money if available for reclamation work in the event a company defaults on its payment, according to the Division. The contractor, like the furloughed employees, is not being paid and has warned state officials “it will be hard to keep up their environmental protection measures if they can’t pay for supplies, fuel and wages,” but they will continue to work. The Division said it could fund the contractor as a stopgap measure and seek reimbursement later.

Mine ordered to mitigate environmental harm; reclamation contractor is working without pay Read More »

hudson-logo

Surety’s claims against bank fail [Hudson]

A surety that paid out more than $3.7 million in claims failed in its attempt to sue the principal’s bank because its claims were time-barred, a negligence claim failed as a matter of law, there was no confidential relationship as required for a constructive fraud claim and the elements of breach of trust, constructive trust or accounting were not satisfied. Background In 2009, Andy Persaud, president of Persaud Companies Inc., or PCI, opened an account at the Bank of Georgetown. In December 2010, Persaud established a bonding program with Hudson Insurance Company, a surety that agreed to issue payment and performance bonds on PCI’s behalf. In the course of underwriting the bonding program, Hudson’s agent obtained from Persaud documents showing all banks with a security interest in PCI as well as the promissory note and loan documents between PCI and the bank. In late 2011, Persaud requested an expansion of the bonding program. Hudson agreed to execute an amended general indemnity agreement on two conditions: first, that an additional indemnitor be added, and second, that all funds from contracts relating to the agreement run through a third-party escrow account. Gary W. Day agreed to serve as a second indemnitor in exchange for payment to Day of 1% of the face amount of all bonds issued by Hudson. A few months later in the spring of 2012, Hudson began receiving claims on PCI’s projects. Hudson ultimately lost $3.7 million by paying out claims related to PCI. Hudson and Day obtained default judgments against PCI and Persaud, who is believed to be penniless. Day obtained the assignment of Hudson’s claims against the bank. Day asserts that, had Hudson been aware of the nature of the banking relationship between Persaud and the bank, it would never have agreed to issue the bonds on which it suffered losses. Analysis The district court held Day failed to state a claim and so dismissed his suit, and, alternatively, granted summary judgment finding all of Day’s claims time-barred. With respect to the latter, it recognized that, under Maryland law, an action only accrues when the claimant in fact knew or was on inquiry notice of the alleged wrong. The court concluded that Day was on inquiry notice no later than October 2011, when Day, Hudson, and Persaud executed the amended general indemnity agreement. At that time, Hudson was already concerned about the state of Persaud’s finances and possessed the bank’s UCC filing and the loan documents memorializing the agreement between the bank and Persaud. We agree with the district court’s analysis. The latest Day could have filed suit within the limitations period was therefore October 2014; he did not actually file suit until April 2016. Day’s claim is therefore time-barred. We also agree that Day’s complaint fails to state a claim. The district court rejected Day’s negligence claim on multiple grounds, concluding that the statute did not establish a duty to Day on the part of the bank and that Maryland law precluded Day’s recovery in tort for purely  economic losses. Next, the court dismissed Day’s attempts to sue directly under the anti-assignment act, concluding that Day lacked a cause of action and that there was no authority to support his argument that he may be subrogated to the government. Day’s constructive fraud claim also failed because, as the district court explained, Day could show neither violation of a duty nor the existence of a confidential relationship between Day and the bank, both necessary prerequisites to stating a constructive fraud claim. Finally, the district court properly dismissed Day’s counts seeking equitable relief, noting that Day could not meet the elements of breach of trust, constructive trust or accounting. This analysis is sound. Affirmed. Day v. United Bank, Appeal No. 18-1961, Feb. 20, 2020. 4th Cir. (per curiam), from DMD at Greenbelt (Xinis). David Hilton Wise for Appellant, Richard E. Hagerty for Appellee. VLW 020-2-036. 6 pp.

Surety’s claims against bank fail [Hudson] Read More »

Talisman Casualty Denied Diversity Jurisdiction Of Protected Cell Series LLC In National WW II Museum Case

A captive insurance company (usually just referred to as a “captive” in short) is an insurance company that is set up to provide for the insurance needs of its owners, and them only. There are many types of captives, and they can be organized in many ways, most typically as corporations but also as LLCs and some other more exotic types of entities. A captive can be organized — and many are — as a Series LLC. That particular form of LLC is very complex, and consists of a larger LLC (called the “series organization”) which is then subdivided into many smaller units (called “protected series”). Very similar in many respects to a parent/subsidiaries structure, Series LLCs offer certain benefits in the captive insurance field when it comes to insurance licensing and capital requirements. In 2016, the National WW II Museum (New Orleans) ordered a steel truss canopy from Gava Steel, Inc., and paid about $3 million. To protect itself, the Museum obtained a bond in the same amount from Talisman Casualty Insurance Company, LLC, which is purportedly managed (which is different than owned) by Jeffrey Schaff of Louisiana. For whatever reason, Gava Steel didn’t perform as promised, and the Museum made a claim on Talisman’s bond. Claiming that no valid bond was ever issued, Talisman didn’t honor the bond. So, Museum sued Talisman in the Civil District Court of the Parish of Orleans. Talisman then removed the case to the U.S. District Court for the Eastern District of Louisiana. claiming diversity jurisdiction since Talisman was organized in Nevada and the Museum is in Louisiana. As an aside, federal law requires what is known as “complete diversity” of citizenship in order for diversity jurisdiction to apply, i.e., no plaintiff can be from the same state as any defendant. Where a party is an LLC, the court looks through the LLC to see where its members are located. Museum then filed a motion to remand the case back to the Parish of Orleans court, arguing that because Talisman was an LLC, and because its (undefined) owner is a resident of Louisiana, both the plaintiff and the defendant were located in Louisiana and so there was no complete diversity such as would support diversity jurisdiction in the federal court. Talisman made two arguments why complete diversity was present. The first argument was that because Talisman was a licensed captive insurance company, it should be treated as a corporation with its location in Nevada, instead of as an LLC where the jurisdiction of its owner (Schaff) would place it in Louisiana. Second, and most interestingly, Talisman argued that it was a Series LLC, that only protected cell #01 was potentially liable on the bond, and that cell #01 didn’t have any members at all, much less any members in Louisiana — other of Talisman’s protected cells might have Louisiana members, but not protected cell #01. To support this second argument, Talisman submitted an affidavit which said that protected cell #01 had no members. All this resulted in the opinion of the U.S. District Court that I shall next relate. The court took these arguments in reverse. As to Talisman’s argument that protected cell #01 had no members, that argument immediately backfired. The court pointed out that under long-standing law, if an LLC has no members, then it is “stateless”, and a stateless LLC cannot establish diversity of jurisdiction. Since Talisman had submitted an affidavit that protected cell #01 had no members, it had effectively shot itself in the foot on this issue. Talisman’s other argument, that even though it was organized as an LLC, Talisman should be treated as a corporation because it was a licensed captive insurance company, also fell on deaf ears. The court noted that 175 years ago, the U.S. Supreme Court allowed corporations to be treated as citizens for purposes of diversity citizenship, but since then the Supreme Court has consistently restricted business entities’ access to the federal courts by way of diversity jurisdictions, to which Talisman’s argument for an expansion of such jurisdiction clearly ran counter. Moreover, in footnote 2, the court pointed out that the Museum had sued Talisman generally, and not just protected cell #01, and Talisman did in fact have its only member in Louisiana such that complete diversity was destroyed. ANALYSIS What this case highlights is that there are many nuances about Series LLCs that are yet to be discovered. While it may be possible to structure things with a Series LLC that could not be so structured with any other form of business entity, all the ramifications of doing that are probably impossible to predict. Here, for whatever reason, protected series #01 was structured in a way that it did not have any “members” in the sense that an ordinary LLC typically would, but that ended up having a negative repercussion as it defeated Talisman’s attempt to move the case out of Louisiana state court and into the federal courts. Yes, Series LLCs are extremely versatile: They are also dangerous. As I have pointed out on numerous occasions, if an ordinary LLC is a Cessna 172 with few systems and controls, a Series LLC is a 747 with hundreds of systems and controls thus making it very easy for a fatal mistake to be made. Or, as my friend and colleague Tom Rutledge is so fond of pointing out, for most folks the creation of a Series LLC is like giving an Uzi to a three-year old. On a more practical note, Talisman’s argument that protected series #01 did not have any members is probably technically incorrect, for the reason that in the absence of members the series organization itself is the member, in this case being Talisman the main company. Thus, the court could probably have correctly held that protected series #01’s member was Talisman, and Talisman’s member was Schaff, and so therefore protected series #01 was located in Louisiana for purposes of testing diversity jurisdiction. An alternative construct would be that without members, protected series #01

Talisman Casualty Denied Diversity Jurisdiction Of Protected Cell Series LLC In National WW II Museum Case Read More »

supreme-court-canada

Supreme Court of Canada could review ‘joint and several liability’ clause in surety bond [Intact]

he Guarantee Company of North America wants to take a disputed claim on a 20-year-old performance bond to the Supreme Court of Canada. The top court announced Feb. 7 that The Guarantee is applying for leave to appeal HOOPP Realty Inc. v. The Guarantee Company of North America, released this past November by the Court of Appeal of Alberta. It all began in 1999 when The Guarantee wrote a $3.9-million performance bond for a warehouse in Alberta. It was a design-build project owned by HOOPP Realty, part of the Healthcare of Ontario Pension Plan. A problem with a floor in the building – completed in 2000 – led to a dispute been HOOPP Realty and a contractor, AG Clark Holdings Ltd. HOOPP Realty’s lawsuit against Clark was thrown out of Alberta court in 2013 because of mandatory arbitration clauses in the design-build contract and the statute of limitations. HOOPP Realty is now trying to recover some of its costs under the performance bond written by The Guarantee. The 1999 bond was replaced in 2004. The Guarantee argued that HOOPP Realty cannot claim on the performance bond, unless there is an enforceable claim against Clark Builders. The Guarantee also argued that a surety is entitled to raise any defence that the principal could raise. A surety bond is a three-way contract between a surety, principal and obligee. The principal, often a construction contractor, is the surety’s client. If the principal fails to fulfill the terms of a separate contract with the principal’s customer (the obligee, often a real estate developer), then the obligee could make a claim with the surety. In 2018, Justice Michael Lema of the Alberta Court of Queen’s Bench ruled that the Guarantee remains liable to the obligee, HOOPP Realty, under the bond that The Guarantee wrote for Clark. This despite the fact that Clark as principal is not liable to HOOPP Realty as obligee. That decision was upheld in the Court of Appeal of Alberta’s unanimous ruling released Nov. 19, 2019. On the original project, Clark ultimately corrected a floor problem. But then HOOPP Realty tried to sue Clark to recover investigation, consulting and engineering costs – which were not broken down in the court ruling. That dispute dragged on for more than 10 years. The Guarantee (acquired in 2019 by Intact Financial Corporation) is arguing that a company writing a surety bond is only liable to an obligee if the principal is. If the Supreme Court of Canada grants The Guarantee leave to appeal, it means the top court could potentially reverse last year’s ruling against The Guarantee. The Supreme Court of Canada could also deny leave to appeal, meaning the Court of Appeal of Alberta ruling is final. Ultimately, HOOPP Realty’s lawsuit against Clark was dismissed without any ruling on whether Clark Builders was liable to HOOP for its claim for investigation, consulting and engineering costs. “If The Guarantee Company had intended to make its obligations conditional upon HOOPP Realty pursuing Clark Builders, it should have specified that in the bond,” the Court of Appeal of Alberta found. There was no clear wording in the surety bond that that makes the liability of The Guarantee Company contingent on the liability of Clark Builders, the Court of Appeal of Alberta observed. Instead, the bond stipulates that The Guarantee Company and Clark Builders are ‘jointly and severally’ liable under the bond. “This signals that The Guarantee Company owes freestanding obligations to HOOPP Realty under the performance bond, and that its obligations are not merely concurrent with or secondary to the obligations of Clark Builders.” The 2019 Court of Appeal of Alberta ruling – by judges Frans Slatter, Frederica Schutz and Ritu Khullar – was attributed to “the court.” In his 2018 ruling, Court of Queen’s Bench Justice Lema said the performance bond could have stipulated that if HOOPP’s cause of action against Clark is extinguished, that The Guarantee has no further liability to HOOPP. The bond also could have had any other provision clearing The Guarantee of liability if Clark obtained protection from its liability in any way. The Guarantee had argued that the joint and several liability provision of the bond was meant to ensure that if the surety makes a payment, the surety can recover from the principal. “The general surety law does not allow a surety to invoke every defence available to the principal debtor,” Justice Lema countered in his 2018 ruling. “The ‘joint and several’ clause confirms that HOOPP has a separate and distinct claim against [The Guarantee]. At worst, it does not detract from that position.”

Supreme Court of Canada could review ‘joint and several liability’ clause in surety bond [Intact] Read More »

Nationwide attorney: Insurer not surety of shop’s work, but will pay until right

An attorney for Nationwide told the Pennsylvania Supreme Court last month that the insurer didn’t count as a surety responsible for the quality of its repair shops’ work. The Nov. 21 comments by Derecht lawyer Robert Heim during oral argument for Berg v. Nationwide provide consumers — and DRP shops — a view into how a carrier might view a DRP relationship. (Special thanks to PCNTV, whose video coverage of the oral arguments identified speakers and allowed us to capture what was said at the proceedings.) The Supreme Court had agreed in March to re-examine Pennsylvania Superior Court 2-1 decision in the long-running case. The Superior Court had determined Common Pleas Judge Jeffrey Sprecher overreached in finding Nationwide’s behavior bad faith and awarding $21 million in damages. Nationwide had suggested plaintiffs Daniel and Sheryl Berg (who died during the course of the litigation) have their 3-month-old, leased 1996 Jeep Grand Cherokee repaired at one of its direct repair program shops following a 1996 crash, according to a 2017 summary of the case by collision industry attorney Erica Eversman and another summary by plaintiffs’ attorney Mayerson Law. Heim said Nov. 21 the record showed that plaintiff Daniel Berg selected the Blue Ribbon shop, Lindgren Chrysler-Plymouth, based on prior work it had performed. Lindgren estimated Sept. 10, 1996, the repair would cost $12,326.50, but also had called the Grand Cherokee a total loss given its frame damage. Nationwide opted not to total the vehicle, and a claims log item notes: “REPAIRS ARE APPROXIMATELY 50% of ACV NATIONWIDE WILL NEVER RECOVER THE DIFFERENCE IN SALVAGE VALUE.” Four months later, the Jeep Grand Cherokee work was finished, with some of the frame work outsourced to a third party. The vehicle was unsafe, but Nationwide either didn’t inspect it as it should have or did inspect it and didn’t tell the Bergs, Sprecher concluded in 2014. Sprecher in 2015 decried Nationwide’s attempt to use a “scorched earth” litigation policy costing $3 million in its own attorneys fees and notes “several legal duties and fiduciary obligations that it recklessly disregarded.” He awarded $18 million plus another $3 million based on what Nationwide paid in its own attorneys. The Superior Court’s overturning of Sprecher’s decision appears to mean that Nationwide would only be responsible for the $295 in actual damages a jury awarded for finding Nationwide violated Pennsylvania’s unfair trade practices law. The jury also determined Lindgren should have to pay $1,925 in compensatory damages. Duty just to pay? Berg sued Lindgren and received a judgment for poor repairs, Heim told the Supreme Court Nov. 21, “which is the way this should have worked. Nationwide’s duty, under its policy, was to pay.” Pennsylvania Supreme Court Justice David Wecht said an “interesting” legal issue involved whether there was a “guarantee” and/or “heightened duty” in a DRP network. Presumably in developing such a network, Nationwide procedures exist to “inspect these shops and maintain certain standards,” Wecht said. Heim said there was a “heightened guarantee” over what support the consumer would receive should they pick a non-network body shop. If the non-Blue Ribbon body shop erred, the customer’s recourse would be to take action against the shop, Heim said. But using a DRP shop offered a “heightened guarantee” in which Nationwide would stand behind such a consumer until that repair was done, he said. Asked by Justice Max Baer if Nationwide agreed that it was the “surety” of its Blue Ribbon direct repair shops, Heim said “no.” How could the carrier offer a guarantee the work would be appropriate but not be the “guarantor of the work,” Baer asked. The insurer offered a guarantee that if their DRP shop’s work was wrong, “they will continue to pay for it until it is done correctly,” Heim said. “That’s really what it is, judge.” Plaintiff’s attorney Kenneth Behrend of Behrend & Ernsberger also addressed Nationwide’s duty regarding repair quality. However, he largely seemed to tie that responsibility to the insurer’s election to repair the Jeep rather than Lindgren being a DRP shop. https://www.repairerdrivennews.com/2019/12/10/nationwide-attorney-insurer-not-surety-of-shops-work-but-will-pay-until-right/

Nationwide attorney: Insurer not surety of shop’s work, but will pay until right Read More »

Contractor named to finish East Gadsden Community Center [Main Street]

A new contractor has been chosen to finish work on the long-delayed East Gadsden Community Center. At Tuesday’s meeting of the Gadsden City Council, it authorized an agreement with Bob Smith Construction, Inc. to complete the remaining work under the original contract for the project The original bid for the project was $5.5 million, and City Attorney Lee Roberts said the city has $3.5 million remaining that has not been spent. He said the cost for completion will be $5.2 million, but the bonding company will cover the difference between the amounts. “Assuming there are no further hiccups out there, this project will be completed without any further spending of taxpayer money,” Roberts said. Groundbreaking on the project was held in February 2018, and the plan was to have the project completed in about nine months. However, Roberts said work on the new community center stopped during construction, and the city engaged the surety company earlier this year to step in and help finish the project. All public construction projects by the city are bonded through a surety company that ensures the project is completed by the terms of the contract, which includes things like quality and timeliness. Roberts said NGM Insurance Company worked with the city on the claim. “They have secured another contractor that is familiar with our city engineer and has a good past working with [him],” Roberts said. “We have entered into an agreement on how we’re going to finish the project.” In addition to the money covered by the bonding company, the city has received some money in liquidated damages, which hopefully will offset additional architecture fees and any unforeseen costs. Roberts said the new contractor has a year to finish the project, but he has told the city it will hopefully be finished before then. City Engineer Heath Williamson said after the meeting that he expects work to start after the first of the year as there is still paperwork to be done. Another infrastructure issue got attention at the meeting as District 3 council member Thomas Worthy talked about street lights being out on Tuscaloosa Avenue. Worthy said there are 19 lights out from Henry Street to 10th Street, and the first resolution to fix them came up in 2018. “I just don’t understand — we can find money for any project we want to have except for doing something in District 3,” said Worthy, who said he had been told by Mayor Sherman Guyton weeks ago that the city would fix the lights, and they shouldn’t have to wait until a new budget comes around. Guyton said it would have to be added to the city’s next budget, and he was mistaken when he said there was money already available. “To portray me as not [doing] anything for Carver, we’ve put more than $2 million into that whole strip since I’ve been in office,” said Guyton, who also listed several of those projects. “I’m glad to do that just like any other part of town, but it’s not in the budget and it’ll have to wait,” he said. The city also approved a memorandum of understanding regarding the use of Everbridge by Safeware — software that allows the sending of public alerts. The memo allows the Gadsden/Etowah Emergency Management Agency to split costs for the service with DeKalb, Marshall, Lauderdale, Calhoun, Cleburne and Morgan counties. Each agency’s cost will be determined by its population. https://www.gadsdentimes.com/news/20191210/contractor-named-to-finish-east-gadsden-community-center

Contractor named to finish East Gadsden Community Center [Main Street] Read More »

Scroll to Top
Document